Every work funded by DMFT Jamtara with its cost, agency and physical progress. Delayed works stay flagged until they recover.

Last updated: 06 Oct 2026 Illustrative data
Works listed
30
Completed
10
On track
13
Delayed
5
Value of works
₹30.3Cr
Works by status
Works by status
Works
Completed10
On track13
Delayed5
Sanctioned2
Physical progress Number of works in each progress band
Physical progress
Works
0–24%5
25–49%5
50–74%6
75–100%14

Progress and status

Showing: 30

  • Solar mini water supply, Dhobna and 6 villages

    Nala · Drinking water

    On track ₹186.5 lakh
    82%
  • Labour room and OT upgrade, CHC Kundhit

    Kundhit · Health care

    Completed ₹142.0 lakh
    100%
  • Smart classrooms in 24 upgraded high schools

    Jamtara · Education

    On track ₹210.0 lakh
    64%
  • PCC road and drain, Mihijam ward 4 to 7

    Jamtara · Physical infrastructure

    Delayed ₹96.4 lakh
    38%
  • Anganwadi centre buildings, 12 locations

    Fatehpur · Women and child welfare

    On track ₹118.8 lakh
    71%
  • Check dams on Ajay river tributaries

    Narayanpur · Irrigation

    Delayed ₹74.2 lakh
    22%
  • Sewing and tailoring centre for SHG women

    Karmatanr · Skill development

    Completed ₹38.5 lakh
    100%
  • Mobile medical units for mining belt villages

    Nala · Health care

    On track ₹64.0 lakh
    90%
  • Plantation and dust barrier along quarry roads

    Kundhit · Environment

    Sanctioned ₹42.6 lakh
    0%
  • Deep borewells with overhead tanks, 15 tolas

    Fatehpur · Drinking water

    On track ₹132.3 lakh
    47%
  • Solar mini water supply, 9 tolas of Kundhit

    Kundhit · Drinking water

    Completed ₹92.4 lakh
    100%

    Drinking Water and Sanitation Dept. · Started Nov 2024

  • Hand pump repair campaign, Narayanpur

    Narayanpur · Drinking water

    Completed ₹28.6 lakh
    100%

    Drinking Water and Sanitation Dept. · Started Mar 2025

  • Water quality labs in 12 high schools

    Jamtara · Drinking water

    On track ₹18.0 lakh
    56%

    Drinking Water and Sanitation Dept. · Started Jan 2026

  • Overhead tank and pipeline, Mihijam ward 9

    Jamtara · Drinking water

    Delayed ₹76.8 lakh
    31%

    Drinking Water and Sanitation Dept. · Started Aug 2025

  • Silicosis screening camps for quarry workers

    Nala · Health care

    Completed ₹22.5 lakh
    100%

    Health Department · Started Feb 2025

  • Labour room upgrade, CHC Fatehpur

    Fatehpur · Health care

    On track ₹118.0 lakh
    58%

    Health Department · Started Oct 2025

  • Health sub-centre building, Bindapathar

    Narayanpur · Health care

    Delayed ₹46.2 lakh
    15%

    Health Department · Started Sep 2025

  • Classroom and toilet renovation, 18 schools

    Fatehpur · Education

    On track ₹330.0 lakh
    12%

    Education Department · Started Aug 2026

  • Residential coaching for Class 11 and 12

    Jamtara · Education

    On track ₹84.0 lakh
    75%

    Education Department · Started Jun 2025

  • Science labs in Kasturba Gandhi Balika Vidyalayas

    Karmatanr · Education

    Completed ₹54.0 lakh
    100%

    Education Department · Started Dec 2024

  • Nutrition kits for pregnant women

    Kundhit · Women and child welfare

    On track ₹40.0 lakh
    80%

    Social Welfare Department · Started Jul 2025

  • Bamboo craft unit for SHGs

    Narayanpur · Skill development

    Completed ₹26.4 lakh
    100%

    JSLPS · Started Jan 2025

  • Heavy machinery operator training

    Nala · Skill development

    On track ₹34.0 lakh
    45%

    Labour Department · Started Feb 2026

  • Water sprinklers on Nala haul roads

    Nala · Environment

    Completed ₹45.0 lakh
    100%

    District Mining Office · Started Apr 2025

  • Assistive devices camp, all blocks

    Karmatanr · Elderly and disabled welfare

    Completed ₹82.0 lakh
    100%

    Social Welfare Department · Started May 2025

  • Community sanitary complexes, 34 hamlets

    Kundhit · Sanitation

    On track ₹120.0 lakh
    66%

    Drinking Water and Sanitation Dept. · Started Sep 2025

  • Culverts on quarry-traffic roads

    Fatehpur · Physical infrastructure

    Delayed ₹240.0 lakh
    27%

    Rural Works Department · Started Jun 2025

  • PCC road, Kundhit to Bagdahri

    Kundhit · Physical infrastructure

    Completed ₹162.0 lakh
    100%

    Rural Works Department · Started Oct 2024

  • Pond renovation, 48 villages

    Karmatanr · Irrigation

    On track ₹124.0 lakh
    52%

    Minor Irrigation Department · Started Nov 2025

  • Solar street lights, 1,600 points

    Narayanpur · Watershed and energy

    Sanctioned ₹180.0 lakh
    0%

    JREDA · Started Sep 2026